Got a Seawall Citation? Deadlines and What to Do Next

Broward cities can cite a seawall that lets tide water onto a neighbor or the street. Most give 60 days to show progress and 365 days to finish. Here is how the clock works and how to use the time well.

Updated October 26, 2026 · Sources linked throughout and listed below · General information, not legal or engineering advice

Why seawalls get cited

Under Broward County's model code, a tidal flood barrier is presumed to be in disrepair if tidal water flows through or over it onto a neighbor's property or the public right-of-way, and failing to keep it in good repair is a citable offense. Letting tidal water trespass onto other property is declared a public nuisance (Broward County Code Sec. 39-407). Most waterfront cities in the county adopted the same language. Fort Lauderdale also says it cites owners whose seawalls contribute to roadway tidal flooding (City of Fort Lauderdale), and Pompano Beach says a property reported and documented to flood adjacent roads or neighbors will be cited (city flyer).

King tide season, roughly September through November, is when most overtopping is seen and reported.

The deadlines, city by city

Seawall citation deadlines (checked October 25, 2026)
CityShow progressFinishSource
Fort Lauderdale60 days365 daysOrdinance C-23-05
Hollywood60 days after the citation365 daysSec. 150.30
Hallandale Beach60 days after the citation365 daysSec. 8-90
Wilton Manors60 days365 daysSec. 11-27
Oakland Park60 days from notification365 days from the citationSec. 14-1
Pompano Beach60 days365 days, including permits and final inspectionSec. 151.05, city flyer
Dania BeachAdopted the county-mandated standard in 2021 (Ordinance 2021-027). The county model uses 60 and 365 days; confirm the wording with the city.Sec. 240-30 (Ord. 2021-027), county model
Lighthouse PointSec. 42-381 sets height rules but no citation timeline. Ask the city how it handles overtopping walls.Ordinance 2023-0998

One detail matters a lot: where a cited wall needs a substantial repair, the county model and the cities that follow it require the new wall to be designed, permitted, built and pass final inspection at the required elevation within the same 365 days (Broward County). That year has to cover engineering, a survey, city and county review, and construction.

What to do, step by step

  1. Keep the notice and note the date you received it. Both deadlines run from the citation or notification.
  2. Document the problem. Photograph the overtopping or leak at high tide with the date and time, and the wall at low tide. Those photos help a contractor give a useful first opinion.
  3. Get the wall looked at early. A licensed contractor or engineer can tell you whether a targeted fix will stop the water or whether the job crosses the substantial repair line. See the inspection guide.
  4. Get your elevation. A survey in feet NAVD88 shows how far the wall is from your city's standard. See the Broward County height requirement.
  5. Show progress inside 60 days. The codes ask for progress, not a finished wall. A signed contract, engineering underway or a permit application on file is the kind of step to ask the city about, and keep copies of everything.
  6. Get permits moving. Most cities need a building permit with sealed plans and surveys, and Broward County requires a license for work in the water. See seawall permits and who to call.
  7. Talk to the city if the schedule slips. Call the code enforcement or building contact on your notice before a deadline passes, not after.

This is general information, not legal advice. What counts as progress, and how a city enforces its deadlines, is up to the city. Read your notice closely and ask the city or an attorney about your situation.

Fixes that often stop overtopping

Depending on the wall, options include sealing joints and cracks where water comes through, adding or raising a cap where the wall can carry it, tying into a neighbor's wall to close a gap, and replacing the wall when it is too weak or low to raise. Our cap repair vs. replacement guide covers the trade-offs, and the cost guide shows typical published prices. See seawall repair and seawall cap repair for what that work involves.

Cited and short on time? We connect Fort Lauderdale and South Broward owners with licensed, insured local seawall contractors. Request a free quote and mention the citation date.

Questions owners ask

How long do I have to fix my seawall after a citation in Broward?

In most Broward waterfront cities that follow the county model, including Fort Lauderdale, Hollywood, Hallandale Beach, Wilton Manors, Oakland Park and Pompano Beach, the owner must show progress within 60 days and complete repairs within 365 days. Check the wording in your city's code and on your notice.

Why was my seawall cited?

Usually because tidal water flows through or over the wall onto a neighbor's property or the street. Broward's model code presumes such a wall is in disrepair and treats the water trespass as a public nuisance.

Does a citation mean I have to raise my wall to 5 feet?

Not always. If a targeted repair stops the water, that may be enough. If the fix counts as a substantial repair, the wall has to meet the city's elevation standard, and in most cities that work must be finished within 365 days of the citation.

What counts as progress within 60 days?

The codes do not define it in detail. Ask the city what it accepts, and keep records of each step, such as an inspection, a signed contract, engineering or a permit application.